Project Kenilworth, Bletchley, Milton Keynes
Jan 2017 – Ongoing – Willmott Partnership Homes Ltd – Value undisclosed

MMK were awarded this scheme as part of three schemes within a 1.5 mile radius of each other by Willmott Partnership Homes Ltd.

The initial part of this project is the enabling works including site compound set up, then MMK will utilise an excavator and breaker attachment to break out and remove a vast area of an existing concrete slab and remove from site, followed on by a reduced level dig to enable us to install the storm and foul drainage systems and also a large attenuation system and form the new access road to the site, including all adoptable drainage manholes which will need to be constructed on the Anglian Water network for the main foul and storm connections.

MMK will also be undertaking the housing aspect of the site installing all foundations for all new plots on the development including all brickwork to DPC and all internal drainage and main services etc. MMK also have all external works in their order which includes forming all the new parking bays on the development and all surfacing works which includes the tarmac surfacing and paving surfaces.

MMK have this project on a Labour, Plant and Materials basis including all the Setting Out and surveying covered by MMK Civils Ltd.

Please select an image to see a larger version and scroll through all images