Project Middlesex, Bletchley, Milton Keynes
Feb 2017 – Ongoing – Willmott Partnership Homes Ltd – Value undisclosed

A similar nature to the Kenilworth and Whaddon projects, enabling works, roads and sewers and foundation works to DPC and Section 278 Works on the new housing development.

This project includes a pumping station which will need to be installed by MMK and a main foul drainage connection onto the main highway where MMK will have to work around the existing services in the vicinity and will include all necessary Traffic Management and planning to ensure a smooth process for the main drainage connection.

MMK will be installing a pumped rising main throughout the site due to the levels of the existing drainage and the levels of the new development.

Again on a Labour, Plant and Materials basis including all Setting Out / Surveying.